We are continuing the collaboration that began with the Assaku Rail Baltica road viaduct on another Trev2 Rail Baltica project. This time, we’re contributing to the construction of the Tagadi Viaduct near the village of Kurtna, so that the Riga train can start running soon! We began work in early January. As of today, the main part of the work is nearing completion, and we have built the foundations and bridge piers. Together with Ramirent, we have erected an 8-meter-high formwork for the bridge deck slab at > and completed the reinforcement work; together with our partner Betoonimeister, we have poured approximately 500 m³ of concrete for the deck slab. We resumed the main construction work at the beginning of this year, and the project is expected to be handed over in May. The stairs leading to the fill area and the access slabs still need to be constructed.