Description
AS Maru Metall signed a contract with Ferbeck Industrial Chimenys on the 17th of August in 2012 for manufacturing Eesti Energia the new 300MW power plant chimeny platforms. The contract includes the steel structure manufacturing and the scope of works are approximately 70 tons of steel structures including the ladders, handrails and gratings. The biggest challenge was the manufacturing of 1,7 meters welded beams.