Steel Structures for VKG Uus-Kiviõli Mine Conveyor
Photo: VKG
In September 2026, Viru Keemia Grupp (VKG) officially inaugurated the new Uus-Kiviõli mine, a project valued at EUR 75 million, featuring conveyor steel structures installed a year earlier by Maru THM.
The project scope involved installing the conveyor’s steel structures spanning nearly 6 kilometres from the Uus-Kiviõli mine to the existing Ojamaa mine, including a river crossing. In total, approximately 1,000 tonnes of structural steel were erected.
Client
RBL-REI
Location
Võrnu, Ida-Viru County
Country
Estonia
Volume
Approximately 1,000 metric tons of steel
Executed by
Maru THM OÜ
Field of work
Assembly
Object type
Industrial and production facilities
Year of completion
2025